+55 (11) 3124-1200
─────
UTC International constructed over 40 production modules, developing 14 modules simultaneously.
─────
P-47, P-53, P-63, P-25, P-55 (deck box), of Jack Ups P59 e P-60 besides the convertion of 4 VLCC to FPSO and the construction of PPRA1 deck.
EPC contract for CARAPEBA III, fixed platform, including jacket e deck‐box, assembly, integration, commissioning, all testsand pre‐operation.
Conversion of the Semi-Submersible Drilling Unit(SS)P‐25 into the Semi‐Submersible Production Unit P‐25, with a process plant of 100,000 bopd and 115 mmcf/d of natural gas.
Conversion of Floating, Storage & Offloading (FSO) P‐47 into Floating Production, Storage and Offloading (FPSO)P‐47, for the installation of an oil and water treatment unit to export treated oil from the Marlim to the Campos Basin, along the north coast of the State of Rio de Janeiro, Brazil.
EPC: Supply of 8 modules, flare, pipe rack top sides for the FPU P‐53, in Rio Grande‐RS, (Related Company).
EPC contract forfull supply of FPU P‐55, including deck‐box, assembly, integration, commissioning, all tests and pre‐operation (Related Company).
BOT ‐ Supply of Engineering, Materials and Construction Services for Floating Production and Storage UnitP‐63 (Related Company).
EPC contract for the complete construction of P‐59 andP‐60 each one comprises a jack‐up drilling unit weighing around 11,000 tons with three independent retractable legs. The rig is capable of operating at sites with a water depth up to 106 meters and drilling wells up to 9,144 meters (consortium).