+55 (11) 3124-1200

Modules

─────

UTC International constructed over 40 production modules, developing 14 modules simultaneously.

P-43 & P-48, 2001 a 2003
  • Client: PNBV
  • 6 units
  • 8.590 t
P-47, 2002 a 2004
  • Client: PNBV
  • 6 units
  • 1.700 t
P-53, 2005 a 2007
  • Client: QUIP
  • 4 units
  • 1.934 t
P-56, 2007 a 2010
  • Client: PNBV
  • 2 units
  • 2.400 t
P-57, 2008 a 2010
  • Client: SBM
  • 5 units
  • 3.171 t
P-55, 2008 a 2010
  • Client: PNBV
  • 2 units
  • 1.180 t
P-58 & P-62, 2010 a 2012
  • Client: PNBV
  • 14 units
  • 12.416 t

Contracts EPCs

─────

P-47, P-53, P-63, P-25, P-55 (deck box), of Jack Ups P59 e P-60 besides the convertion of 4 VLCC to FPSO and the construction of PPRA1 deck.

Carapeba III, 1993

EPC contract for CARAPEBA III, fixed platform, including jacket e deck‐box, assembly, integration, commissioning, all testsand pre‐operation.

(SS)P‐25, 1996

Conversion of the  Semi-Submersible Drilling Unit(SS)P‐25 into the Semi‐Submersible Production Unit P‐25,  with a process plant of 100,000 bopd and 115 mmcf/d of natural gas.

P‐47, 2005

Conversion of  Floating, Storage & Offloading (FSO) P‐47 into Floating Production, Storage and Offloading (FPSO)P‐47, for the installation of an oil and water treatment unit to export treated oil from the Marlim to the Campos Basin, along the north coast of the State  of Rio de Janeiro, Brazil.

P‐53, 2008

EPC: Supply of 8 modules, flare, pipe rack top sides for the FPU P‐53, in Rio Grande‐RS, (Related Company).

P‐55, 2011

EPC contract forfull supply of FPU P‐55, including deck‐box, assembly, integration, commissioning, all tests and pre‐operation (Related Company).

P‐63, 2013

BOT ‐ Supply of  Engineering, Materials and Construction Services for Floating Production and Storage UnitP‐63 (Related Company).

P‐59 e P-60, 2015

EPC contract for the complete construction of P‐59 andP‐60 each one comprises a jack‐up drilling unit weighing around 11,000 tons with three independent retractable legs. The rig is capable of operating at sites with a water depth up to 106 meters and drilling wells up to 9,144 meters (consortium).